From July 5th – Aug 31st, Crews will be conducting utility construction on W. Bay to Bay Blvd from S. Manhattan Ave to S. Lois Ave.
Should changes in the above listed information be necessary, a public notice with updated timelines will be issued and posted on the project website at www.tampa-neighborhoods.com. Questions can be directed to the project hotline at 813-324-1251.
Shutdown request to take place on Monday 11-6-23 for Tie Ins at:
Shutdown request to take place on Tuesday 11-7-23 for Tie Ins at:
Shutdown request to take place on Wednesday 11-8-23 for Tie Ins at:
Road paving along Kensington Avenue (from Manhattan to E Clark Circle) and along Lois Ave (from Euclid to El Prado) is scheduled.
🗓️ Date: Jan.15 to Jan.19 🕒 Time: 7 am to 5 pm
Residents will be able to return their vehicles to their driveway/ street parking as soon as the asphalt cools. No later than 5 pm.
Thank you for your understanding and cooperation.
Scheduled road paving
Please be advised of the upcoming schedule for final water line tie-in by CoT:
📅 Monday 2/19: Santiago
📅 Tuesday 2/20: Sevilla & Corona
📅 Wednesday 2/21: Leona & San Luis
Expect water interruption from 9AM-5PM on designated days. If affected, you’ll receive a door hanger from CoT.
🚦 Please use adjacent roadways as alternate routes and abide by signs for a smooth and safe commute. Your cooperation is appreciated as we work to enhance our community’s infrastructure.