page-template,page-template-full_width,page-template-full_width-php,page,page-id-23202,page-child,parent-pageid-17012,bridge-core-2.4.6,qode-quick-links-1.0,ajax_fade,page_not_loaded,,hide_top_bar_on_mobile_header,qode-child-theme-ver-1.0.0,qode-theme-ver-23.1,qode-theme-bridge,disabled_footer_top,qode_header_in_grid,wpb-js-composer js-comp-ver-7.9,vc_responsive

Virginia Park Public Notices

From July 5th – Aug 31st, Crews will be conducting utility construction on W. Bay to Bay Blvd from S. Manhattan Ave to S. Lois Ave.

 

  • Lane Closure (Eastbound)

 

Should changes in the above listed information be necessary, a public notice with updated timelines will be issued and posted on the project website at www.tampa-neighborhoods.com. Questions can be directed to the project hotline at 813-324-1251.

 

Shutdown request to take place on Monday 11-6-23 for Tie Ins at:

  • S. Lois Ave and W. Tacon St
  • S. Lois Ave and W. Obispo St

 

Shutdown request to take place on Tuesday 11-7-23 for Tie Ins at:

  • S. Lois Ave and W. San Pedro St
  • S. Lois Ave and W. San Juan St

 

Shutdown request to take place on Wednesday 11-8-23 for Tie Ins at:

  • S. Lois Ave and W. Santiago St
  • S. Lois Ave and W. Bay to Bay Blvd

 

Road paving along Kensington Avenue (from Manhattan to E Clark Circle) and along Lois Ave (from Euclid to El Prado) is scheduled.

🗓️ Date: Jan.15 to Jan.19 🕒 Time: 7 am to 5 pm

Residents will be able to return their vehicles to their driveway/ street parking as soon as the asphalt cools. No later than 5 pm.

Thank you for your understanding and cooperation.

 

Scheduled road paving

  • 🗓️ Date: Feb. 19 to 27 – S. Lois Ave (W. El Prado Blvd to W. Bay to Bay Blvd.)
  • 🗓️ Date: March 18 to 29 – S. Grady Ave (W. Kensington Ave to W. Bay to Bay Blvd.) & S. Clark Ave (W. Sevilla St. to W. Bay to Bay Blvd.)

 

Please be advised of the upcoming schedule for final water line tie-in by CoT:

📅 Monday 2/19: Santiago

📅 Tuesday 2/20: Sevilla & Corona

📅 Wednesday 2/21: Leona & San Luis

Expect water interruption from 9AM-5PM on designated days. If affected, you’ll receive a door hanger from CoT.

🚦 Please use adjacent roadways as alternate routes and abide by signs for a smooth and safe commute. Your cooperation is appreciated as we work to enhance our community’s infrastructure.